Monday, June 8, 2015

Finished and Ready to Fly

Finshed and ready to fly!  After 3 years 2 months 2 weeks and 2 days (March 23 2012 - June 8 2015) and over 2000hrs of work.

The plane is finally complete.






Interior lights on and the wing walk light in the door shining down. It all looks really nice lit up.








Friday, October 4, 2013

Completed Structure Overview (840.25hrs)

Time for another update!

It's getting a little difficult to show what I'm currently working on since I can't really highlight the brake lines or control system parts, among other things. A section that is coming up is the flap system so that area is highlighted red. I still need to build the rear seats and work on the upper cabin. I should be ordering the finishing kit soon.


840.25 hrs Total Building Time  
548.25  hrs is a mixture of tail and fuselage (still in work)
    292.0 hrs of the total belong to the Wings (includes times listed below)
       75.25 hrs to the Fuel Tanks
       25.5 hrs to the Ailerons
       26.25 hrs to the Flaps
Blue is complete. Red is in work.

Wednesday, August 14, 2013

Completed Structure Overview (755.0hrs)

I wanted to make another overview post to show a little more accurately the parts I am working on. Currently, I have a lot of sections I'm working through simultaneously and will also be installing things that aren't in the plans.

For example, I'm working on: the step install, finishing the side skin vent doors, installing the heater boxes, building the upper forward fuselage, installing the luggage area floors, insulation and conduit, and the com antenna installs. So there is a lot of work coming up and I wanted to represent that in the Completed Structure Overview as best I could.

755.0 hrs Total Building Time    463.0  hrs is a mixture of tail and fuselage (still in work)
    292.0 hrs of the total belong to the Wings (includes times listed below)
       75.25 hrs to the Fuel Tanks
       25.5 hrs to the Ailerons
       26.25 hrs to the Flaps


Tuesday, July 16, 2013

Completed Structure Overview (732.5hrs)

Now that the wings are complete it's time for an update to the big picture. The next step is hard to depict. I'll be working on the static lines in the tailcone and then attaching the tailcone to the fuselage, so I highlighted the area where it attaches as in work.

 732.5 hrs Total Building Time
   440.5 hrs is a mixture of tail and fuselage, both still have work to be done on them
   292.0 hrs of the total belong to the Wings (includes times listed below)
       75.25 hrs to the Fuel Tanks
       25.5 hrs to the Ailerons
       26.25 hrs to the Flaps
  
 Blue is completed and red is in work.
 

Wednesday, May 22, 2013

Completed Structure Overview (655.25hrs)

I completed another part so it's time for an update to the big picture. I'm leaving the Fuel Tanks as "in work" until they get tested, so those are still highlighted red. I finished the ailerons so those turned blue. And I'm starting on the flaps, so I went ahead and highlighted those as "in work".

655.25 hrs Total Time Building
  214.75 hrs of the total belong to the Wings (includes tank time)
     75.25 hrs solely to the Fuel Tanks
     25.5 hrs solely to the Ailerons
  440.5 hrs is a mixture of tail and fuselage, both still have work to be done on them


 As always blue is completed and red is in work.
 

Friday, April 26, 2013

Completed Structure Overview (626hrs)

Time for an update to the big picture. I'm leaving the Fuel Tanks as "in work" until they get tested, so those are still highlighted red. And I'm starting on the ailerons tomorrow, so I went ahead and highlighted those as "in work" as well.

626 hrs Total Time Building
185.5 hrs of the total belong to the Wings (includes tank time)
75.25 hrs solely to the Fuel Tanks
440.5 hrs is a mixture of tail and fuselage, both still have work to be done on them

 
As always blue is completed and red is in work.