Monday, February 11, 2013

Completed Structure Overview (534.25hrs)

WOW! I have surpassed 500hrs. So maybe I'm 1/4 of the way done? Who knows.

93.75hrs of that belong solely to the wings the remaining 440.5hrs is a mixture of tail and fuselage both still have work to be done on them. So, better to say, I'm 25% complete and 90% left to go. I have to attach the tail to the fuselage, install the upper canopy, build the upper fuselage, control linkages, break lines, fuel lines, aileron controls, rudder controls, order the avionics, run wiring, order the finishing kit, install the trim servo, install the battery, floor panels, baggage panels, windscreen, pitot tubing, static tubing............

As always blue is completed structure and red is in work.

No comments: