Wednesday, May 22, 2013

Completed Structure Overview (655.25hrs)

I completed another part so it's time for an update to the big picture. I'm leaving the Fuel Tanks as "in work" until they get tested, so those are still highlighted red. I finished the ailerons so those turned blue. And I'm starting on the flaps, so I went ahead and highlighted those as "in work".

655.25 hrs Total Time Building
  214.75 hrs of the total belong to the Wings (includes tank time)
     75.25 hrs solely to the Fuel Tanks
     25.5 hrs solely to the Ailerons
  440.5 hrs is a mixture of tail and fuselage, both still have work to be done on them


 As always blue is completed and red is in work.
 